Wednesday 21 October 2015

"Minafon" - week 15, Wednesday

To summarise today's progress:

exterior colour (Pinwheel) - looking good

grass pavers being delivered (that's work for me)

1st coat on deck and steps - another 2 to go 

  • Exterior painting complete - just a few "post tiler" touch-ups to complete interior
  • Deck and front porch timber have first coat - second goes on Friday
  • the grass-pavers arrived for the driveway
  • electrical fit-out well under way - quite a few lights, fans power-points installed.
  • tiling in ensuite almost done and start made on bathroom
  • we visited the electrical supplier and changed strip lights in bedroom to 5xdownlights - neater.
  • external taps done - more plumbing fit-out tomorrow
  • sorted the removalists for 13th and also phone/internet connection for same day. simple.