Timetable for the next three weeks:
- next week, electrical fit-out, plumbing fit-out all completed and completion of tiling.
- last coats put on decking and railings
- Air-con all goes in Friday
- following week (2nd November+) - Peter Polly on his own to do floors - needs until Friday to complete and no-one else allowed in!
- 9th November, carpets laid in bedrooms
- 10-12th cleaning and fly-screening done
- 13th - move in!