"Minafon" - week 10, Tuesday

OK - all back on track. The cladding has been delivered, along with the brush box floorboards and the crew were all there today working on the internal gyprocking which is now almost finished.

Front door is also installed. Steve anticipates the external cladding will be done this week and then early next week the flooring goes in - then the plasterer comes in to do his work and  following that the painter comes in to do the ceilings and seal the walls. This is followed by the internal fit-out - kitchen, laundry, doors, skirting etc so we can see the end approaching on time. Spoke with Steve re the stairs (he will order iron bark treads) and stringers (galvanised steel).Better start sorting things out here!!

Front door installed

Brush Box flooring all delivered

The brush box flooring - looks beautiful!