Tuesday 17 November 2015

"Minafon" - week 19, Wednesday - Final Blog!

Steve Thomsen came today to remove the site toilet, so we thought that this was the "significant moment" to signal the final "Minafon" blog as the first post had the picture of the newly installed "site facility" symbolising the beginning of the project - 19 weeks ago.

Hope you've had a bit of fun following our big adventure - the first and most certainly the only time we have attempted to build. It was something we always wanted to do (even had concept pictures on the wall of our first government residence at Mt Murchison!!!!) but circumstances never worked in our favour so it took a while (40+ years) - but we've just had a great time and feel very satisfied with the result - after all, we've had enough time and experience to know what we wanted and as I said, we're now good for the next 50 years!

Cheers and some final "settling in" photos:-

The deck - finally no boxes!!!

.....through the front door - Welcome!!

hallway with Claire's painting in its place!

"media room" - bookshelves yet to be installed

living/music room - everything even fits!

"The End" - Steve takes his "facility" to the next job at Boonaroo



Monday 16 November 2015

"Minafon" - week 19, Tuesday

Things are gradually being sorted out - most of the furniture is basically in place so boxes can now be opened and sorted and hopefully there are places for almost everything! I have to do wall shelving in the "media room" and the study before all the books etc can go into place but everything else is good.

The solar panels have been installed but we have to wait until next Monday for Ergon to OK the installation before we go onto the network.

The new turf needs mowing already (we've had about 100mm rain since it went down) but that will just have to wait!

Maybe one or two more "blogs" before we sign off. The "house building adventure" has been a thoroughly enjoyable experience, made so by being clever (and lucky) enough to pick the right designer and builder - we really did not have any concerns or issues throughout. It is great having things just the way we reckon was going to work best for us - no compromises from dealing with existing structures - would we recommend house building to those for whom the circumstances permit and feel inclined to take it on? - absolutely (and we can give you the names of a great house designer and a terrific building company!!)
Our magpie family - Mum and Dad at least - breakfast visit

view from our bedroom....

...and from the kitchen

Sunday 15 November 2015

"Minafon" - week 19, Monday

We're in!!!!!!

We are now back in contact with the world, having the much-waited for text this morning to inform us that we are back on the internet. 

So what's happened since last Monday??? Not a lot really - we just moved house on Wednesday, which went well. The removalists just brought their trucks (yes, two!) down the side and unloaded both at the same time straight onto the back deck - they arrived at about 9.30 and were gone by 12, leaving us with mountains of gear and packing boxes which we are still sorting through of course although we have managed to retrieve most of the essentials of life.

We also managed to lay more turf (it turned up on the removal day so had to be done that evening) and over the weekend installed the letter box so the poor mailman did not have to go cross-country to deliver our mail. 

I'll do a few more blogs as we sort everything out and the place starts to look more civilized, but in summary, it is wonderful to be here - the house is everything we had planned for (and more) and everything seems to be exactly in the right place and working as planned. We have really noticed the quietness and absence of traffic and also the incredible bird life - we have been adopted already by the family of magpies who used to be around when we visited the site and the builders had around them quite frequently. They have already established 5.00pm tea time and when we return from our bike-ride as breakfast-time! The are kookaburras and countless other bird varieties and their sounds in the mornings is just beautiful.

A few pictures of the chaos for you today - some more progress over coming days before we sign off on the blog!
the deck with boxes!!

some signs of progress

"media" room - brush-box  floor has come up beautifully

same deck - fewer boxes!!

Note for Jenny - letter box installed!!

Monday 9 November 2015

"Minafon" - week 18, Monday

Big moment today - we are now the official owners of 65 La Frantz Drive, Tinana!!!!!

Went over to Thomsens this morning with the final cheque and so now we are the owners! Just to make things interesting, the heavens decided to open up and it has been pouring with rain all day and is only just starting to lighten up now (6.00 pm)

So no solar fitted today as planned, no flyscreening fitted either but the carpet guys managed to get in without dragging mud through the place and the carpets look great. We started taking stuff across this afternoon and so more will go tomorrow when hopefully it will be fine. Big moving day is Wednesday.

Will try and get some photos tomorrow - in the meantime, have a look at the beautiful house sign John Howard has made for us - made of "bloodwood" from "Yanco", the property near Surat which Margaret and John owned. Just beautiful and we can't wait to see it in place


Our beautiful house sign

Friday 6 November 2015

"Minafon" - week 17,Saturday

Back again! Since last Monday, we've been doing the preparation for the turf-paving with soil delivered Thursday and the turf Friday afternoon. Lots of work each afternoon or very early morning (out of the heat as much as possible) linking countless pavers together, preparing the ground, setting out etc and then spreading the loam into the pavers and finally on Friday afternoon, laying the turf. More to be done to complete the whole driveway but we've done enough to get us started and will complete the job once we are in.

Meanwhile, Peter (floors) has been sanding and coating, sanding and coating..... finishing the last coat on the floors Friday. They look pretty fantastic.

Also Friday the fellow from Stegbar was there putting in shower screens, bathroom/toilet mirrors and wardrobe doors in bedrooms #2 and #3. They also look great.

The cleaning team moved in today, we settle the final accounts on Monday (ouch) and then start moving in Tuesday with the main stuff arriving from storage Wednesday - the great "adventure" we started so many months ago is almost over!! -- I'll give you the verdict on whether "building a new home" is a good idea next week but I think you can already guess what the answer will be!
slave labour or a labour of love???

ready for the turf.........
.............and there it is!

a sneek look inside - but yet to dry "satin"

Sunday 1 November 2015

"Minafon" - week 17, Monday

A blog after all! Seems that even when "nothing" is supposed to be happening, things still happen!

Peter has sanded the floors and indicated that 1st coat goes on tomorrow, 2nd on Wednesday and 3rd on Thursday. Done.

The Thomsens were also there today doing the driveway and aprons under the front and rear steps along with installing the clothes line. Dave was also there doing some final electrical work apparently. No body ever stops apparently.

Went through a whole lot of "final" stuff with Mandy on the phone this afternoon and she said she will arrange final inspection on Monday which means we can theoretically move in next Tuesday so we've re-booked for next Wednesday (being 11th is better than Friday 13th!!)
driveway done - I now need to add grass-pavers!

1st sanding of floors (black bits are sandpaper)



concrete aprons done for both stairs